Burj Dubai October 15th 2008 photo update

Burj Dubai October 15th 2008 photo update, how the Burj Dubai looks in a sand storm... The last four photos were taken today




Wednesday, October 15, 2008

Burj Dubai October 14th 2008 photo update

Burj Dubai October 14th 2008 photo update, here is six photos taken today of the Burj Dubai they show the progress that has taken place on the spire.







Tuesday, October 14, 2008

Detail diagram of the Burj Dubai October 13th 2008

Detail diagram of the Burj Dubai October 13th 2008, shows progress made to spire section of the Burj Dubai over the past couple weeks.

Monday, October 13, 2008

Burj Dubai video September 1st to 30th progress

Here is a photo video of Septembers progress on the Burj Bubai.

Sunday, October 12, 2008

Burj Dubai October 12th 2008 photo update

Burj Dubai October 12th 2008 photo update, a photo taken today of the Burj Dubai tower spire section.

Saturday, October 11, 2008

Burj Dubai October 11th 2008 photo update

Burj Dubai October 11th 2008 photo update, whoohoo more spire work is taken place here is two photos of the Burj Dubai from today.


Friday, October 10, 2008

Video of Burj Dubai construction site

Here is a small video of Burj Dubai construction site and of the Burj Dubai.

Thursday, October 9, 2008

Burj Dubai October 9th 2008 photo update

Burj Dubai October 9th 2008 photo update, two photos taken today of the Burj Dubai.


Burj Dubai October 8th 2008 photo update

Burj Dubai October 8th 2008 photo update, photos taken today of the Burj Dubai they show the recent work done on tier 22B and the last photo shows each tier number.







Wednesday, October 8, 2008

Burj Dubai October 7th 2008 photo update

Burj Dubai October 7th 2008 photo update, a nice photo of the Dubai skyline and a photo of the Burj Dubai taken today.


Monday, October 6, 2008

Burj Dubai October 6th 2008 photo update

Burj Dubai October 6th 2008 photo update, lots of photos of the Burj Dubai today. Section 22B has begun so the Burj Dubai is now 720.1 meters heigh.






Burj Dubai October 5th 2008 photo update

Burj Dubai October 5th 2008 photo update, The opening of the structural support for the spire can be seen clearly in the last image. I don’t think it will be long before we reach the next tier.





Sunday, October 5, 2008

Burj Dubai October 4th 2008 photo update

Burj Dubai October 4th 2008 photo update, more steel work going on today we can see the new steel beam in place now.



Saturday, October 4, 2008

Arieal photo of Dubai

Here is a nice arieal photo of Dubai, you can see the Burj Dubai easily from a plane if you fly over Dubai.

Burj Dubai October 3rd 2008 photo update

Burj Dubai October 3rd 2008 photo update, here is a photo update on the crane progress.. The first photo shows the size of each section. The second and third photos were taken today.



Friday, October 3, 2008

Burj Dubai October 2nd 2008 photo update

Burj Dubai October 2nd 2008 photo update, here is five photos taken today of the Burj Dubai. The upper crane has been taking down the lower crane and this will most likely take a couple days to complete, so progress on the Burj Dubai might slow for a week or so.





Thursday, October 2, 2008

Burj Dubai October 1st 2008 photo update

Burj Dubai October 1st 2008 photo update, two photos of the Burj Dubai taken today. the spire is coming along nicely and more cladding has been placed on the 4th mech section.


Wednesday, October 1, 2008

Burj Dubai Fountain Announcement and Pics from Today

Back in June, Emaar Properties announced its intention to build a fountain, 275m in length, within the man-made lake at the Downtown Burj Dubai development. The fountain was intended to add to the ambitious downtown area, billed by Emaar as the "new soul of the city," and valued at US $20 billion (AED73 million) in total.

Today, work on the fountain is progressing towards an anticipated opening in the second quarter of 2009, giving it a little time in hand in which to whet the appetite of Dubai's residents and visitors, before the opening of the Burj Dubai itself.

The clock is ticking........

Construction is reportedly on course with 2500 staff currently employed on the fountain and related infrastructure projects. This will rise to 4000 as completion dates approach.

The tower alone supports 7500 staff. The size of the downtown development means that priorities change on a daily basis.

"It's a big collaboration of different projects, and trying to communicate effectively is an ongoing challenge," says fountain project manager Michael Scott.

"Everyone wants to meet their goals so you have to balance what is critical and what is not. What's critical today may not be critical tomorrow. There may be a change of direction on something."

A change in direction is something that the Downtown Burj Dubai development has seen on more than one occasion.