Burj Dubai December 29th photo update, with a rough spire construction schedule.
Here is the spire schedule using the revised schedule from July '07.
- Beginning of steel construction - first week of November - Start of Tier 16 - 585.7 Meters
- Second week of December - Level 160 - Second level of Tier 17 - 611.3 Meters
- Second week of March '08 - Roof 1 - Start of Tier 19 - 643.3
- Second week of April - Roof 2 - Start of Tier 20 - 662.5
- First week of May - Roof 3 - Start of Tier 21 - 681.7
- Fourth week of May - Roof 4/ Spire 1 - Start of Tier 22 - 700.9
- Third week of June - Spire 2 - Start of Tier 23 - 720.1
- Second week of July - Spire 3 - Start of Tier 24 - 739.3 - Beginning of Spire Lifting
- Second week of August - Height begins to increase again
- Third week of September - Final height - 819.0
Saturday, December 29, 2007
Burj Dubai December 29th photo update
Posted by twickline at 6:32 PM 0 comments
Friday, December 28, 2007
Thursday, December 27, 2007
Friday, December 21, 2007
Burj Dubai December 21st photo update
Burj Dubai December 21th photo update, steel is progressing nicely on the Burj Dubai. They almost have the outer ring of the first steel floor completed now.
Posted by twickline at 8:13 AM 0 comments
Thursday, December 20, 2007
Burj Dubai December 20th photo update
Burj Dubai December 20th photo update, Burj Dubai and SZR from Burj al Arab and a nice view of the city of Dubai.The distance between Burj Al Arab and Burj Dubai around 12 km
Posted by twickline at 7:37 PM 0 comments
Subscribe to:
Posts (Atom)