Here is the spire schedule using the revised schedule from July '07.

- Beginning of steel construction - first week of November - Start of Tier 16 - 585.7 Meters
- Second week of December - Level 160 - Second level of Tier 17 - 611.3 Meters
- Second week of March '08 - Roof 1 - Start of Tier 19 - 643.3
- Second week of April - Roof 2 - Start of Tier 20 - 662.5
- First week of May - Roof 3 - Start of Tier 21 - 681.7
- Fourth week of May - Roof 4/ Spire 1 - Start of Tier 22 - 700.9
- Third week of June - Spire 2 - Start of Tier 23 - 720.1
- Second week of July - Spire 3 - Start of Tier 24 - 739.3 - Beginning of Spire Lifting
- Second week of August - Height begins to increase again
- Third week of September - Final height - 819.0




Friday, December 28, 2007

Burj Dubai December 28th photo update

Burj Dubai December 29th photo update, The Burj Dudai is now at Level 157 592.1m / 1943ft




Thursday, December 27, 2007

Burj Dubai December 27th photo update

Burj Dubai December 29th photo update, the first steel floor now has a completed outer ring.



Friday, December 21, 2007

Burj Dubai December 21st photo update

Burj Dubai December 21th photo update, steel is progressing nicely on the Burj Dubai. They almost have the outer ring of the first steel floor completed now.




Thursday, December 20, 2007

Burj Dubai December 20th photo update

Burj Dubai December 20th photo update, Burj Dubai and SZR from Burj al Arab and a nice view of the city of Dubai.The distance between Burj Al Arab and Burj Dubai around 12 km

Wednesday, December 19, 2007

Burj Dubai December 18th photo update #2

Burj Dubai December 18th photo update, The Burj Dubai at night shows how the cladding will look at night time, also a close up of the base and Burj lake.

The third photo is one of the best photo's I've seen yet of the Burj Dubai.



Tuesday, December 18, 2007

Burj Dubai December 18th photo update

Burj Dubai December 18th photo update, Photos of the city of Dubai with Dubai Creek in the foreground these photo's show just how huge the Burj Dubai is. And to think it still has nearly 200 meters more to go before it tops off.


Monday, December 17, 2007

Burj Dubai December 17th photo update

Burj Dubai December 17th photo update, some bueatiful photos of the Burj Dubia.




Burj Dubai December 16th photo update

Burj Dubai December 16th photo update, steel work is progressing and cladding is above the third mechical floor.




Burj Dubai Contruction update December 16th 2007

Cladding has began above the third mechanical floor on the Burj Dubai also their is now water at the Burj bridge.



Sunday, December 16, 2007

Burj Dubai December 15th photo update

Burj Dubai December 16th photo update, The Burj dubai at night and the city of Dubai.


Wednesday, December 12, 2007

Burj Dubai Contruction Plans

These construction plans show in detail what every floor in the Burj Duabi will be used for. They start at the basement and go to the pinnacle. I should point out these plans have the building at 818 meters, when in fact the building will be 819 after the aircraft beacons are installed, other then that the plans are accurate.











Diagram from level 155 to the pinnacle of the Burj Dubai

Updated detail diagram of the Burj Dubai from level 155 to the pinnical.

Tuesday, December 11, 2007

Burj Dubai December 10th photo update

Burj Dubai December 10th photo update, steel has started at the top.



Sunday, December 9, 2007

Burj Dubai December 9th photo update

Burj Dubai December 9th photo update, Burj Dubai from Nad Al Sheba.